Ending a Sprint - Do you know what to do with partially completed PBI?

Updated by Brady Stroud [SSW] 1 year ago. See history

123
<introEmbed body={<> At the end of a Sprint, if a PBI has not been completed and therefore cannot be marked as done: </>} />
  1. Update the Effort to be just what is remaining
  2. If there has been scope creep, but the original Acceptance Criteria has been met, it might be a good opportunity to mark it as done and move any scope creep tasks into a V2 of the PBI, which can then be prioritised in the backlog by the Product Owner